Testing and Commissioning of BIPV Installations
All grid connected BIPV systems (installed in accordance with MS 1837:2005 by the Approved PV Service Providers - APVSPs) must be tested and commissioned prior to physical interconnection to the TNB distribution grid.
The “Testing and Commissioning (T&C)” covers a comprehensive series of tests to confirm that the installation functions as designed and in a safe and effective manner.
TNB shall be a witness to the “Testing and Commissioning (T&C)” and grid connection of BIPV installations by the PV Service Providers concerned.
The T&C form showing the tests to be conducted for the commissioning of the BIV installations is in the following links :
Provision of safety labels and manual
Pictures of PV system installation components