Tuesday September 25, 2007
By MICHAEL CHEANG.
Villagers on an East Coast island are shrinking their carbon
footprints by buying green energy.
THE two giant “fans” rise grandly from the highest point of Pulau
Perhentian Kecil, Terengganu, their manmade presence in sharp
contrast to the lush greenery. Up close, the two white edifices are
even more awe-inspiring, their three blades cutting through the air
with ominous resonance.
The fans are power-producing wind turbines – the first in the
country – and are part of a unique solar-wind-diesel hybrid power
generation system. Installed by Tenaga Nasional Berhad (TNB) and
allegedly the first of its kind in Asia, the hybrid system has a
combined capacity of 650 kilowatts (kW), and is made up of two 100kW
wind turbines, 100kW worth of solar panels as well as two diesel
generators capable of 200 and 150kW respectively.
It also includes a battery that can store up to 480kWh (kilowatt
hour) of power.
TNB Energy Services managing director Rahimuddin Baharudin says
the hybrid system will cut the cost of generating power on the
island by almost 40% from the previous diesel generator system.
“Before TNB came to the island, the villagers relied on their own
small generators. In 2002, TNB installed a diesel generator that
powered the island for 24 hours. However, with rising diesel prices,
we had to find a way to reduce the cost of generating power. One of
the ways is to use renewable energy generated by wind and sun.”
|
|
Windy peak: TNB’s wind turbines rise above
the forest on the highest point of Pulau Perhentian
Kecil. |
At this stage, the hybrid
system is not meant to replace the diesel generators but to minimise
the usage of diesel as a source of electricity. The combination of
solar panels, wind turbines and diesel generator will ensure a
continuous flow of electricity no matter what the weather conditions
are.
“In the day, when we have less wind, the solar panels will cover
the extra load. At night, the wind turbines will be the ones
generating more power. If the solar panels and wind turbines do not
create enough power, the diesel generator will (automatically run
to) compensate for the deficiency.”
Rahimuddin says the system has worked well so far, to the extent
of generating excess energy that has to be burned off with a heater.
For now, the hybrid scheme only provides electricity for Kampung
Perhentian on Pulau Perhentian Kecil, and not the dozens of resorts
that pepper the sandy shores of neighbouring Pulau Perhentian Besar.
The reason? The project comes under the Government’s rural
electrification project and is meant for domestic usage only.
Rahimuddin reckons that it is technically possible for the
resorts to tap the renewable electricity since there is now excess
power. The resorts currently run their own diesel generators.
Project inception
Rahimuddin explains that Terengganu Mentri Besar Datuk Seri Idris
Jusoh was eager to have a renewable energy system on the island
after learning about TNB’s solar hybrid schemes in places such as
the Pemanggil, Aur, Sibu, Besar and Tinggi islands off Johor, and
Kampung Denai in Rompin, Pahang.
|
|
Power of light: The solar panels of Tenaga
Nasional Berhad’s solar-wind-diesel hybrid power generation
system. |
“He has also seen wind farms
in Europe and asked us about the possibility of building wind
turbines on Pulau Kapas and Pulau Perhentian. At the time, we were
aware that Pulau Perhentian has plenty of wind but whether we could
harness that energy was a different matter altogether.
“We had done a study in the area from 1993 to 1999 using a wind
monitoring station. But when we started researching this project, we
found that the data was outdated. The global climate has changed so
much, thanks to global warming, that sometimes we get wind at the
wrong times.”
TNB took six months to reanalyse the data and design the system,
and another six months to build it. The State Government, TNB and
Federal Government each funded one-third of the RM12.76mil cost.
The turbines are designed to harness the winds on Pulau
Perhentian as efficiently as possible. Sensors on the structures
analyse wind directions and speeds, and the turbines will
automatically turn to face the wind.
The entire system is remote-controlled via the Global System for
Mobile communications (GSM) satellite from TNB’s headquarters in
Kuala Lumpur. A few employees are onsite to conduct maintenance on
the diesel generator.
“Most of our solar hybrid stations in Johor and Pahang are
unmanned. But this particular system needs someone to look after the
diesel generator at all times,” says Rahimuddin.
Installation of the wind turbines by contractor Wazlina, was
planned carefully to minimise the environmental impact on the
island, according to Rahimuddin. “We were given conditions by a
committee comprising relevant authorities like Marine Department and
Department of Environment.”
Wazlina environmental consultant Shan Suleiman says although the
worksite was considered only a “small footprint” on the island, they
minimised the impact by not cutting trees unnecessarily, building
silt traps and monitoring siltation caused by earthworks.
However, bringing equipment and materials to the island posed
problems. “The transportation was controlled by the Marine
Department. Whenever we had a barge coming in, we had to report to
them and could only bring the barge in at certain high tides,” says
Wazlina director Mohd Safian Dato’ Salleh. “In the end, it cost us
almost three times the normal amount to bring in the equipment and
materials from the mainland.”
Despite the higher cost of producing the renewable energy, Pulau
Perhentian Kecil villagers are still charged the same electricity
tariffs as on the mainland. This differs from the recently launched
solar-hybrid system on nearby Pulau Kapas. There, TNB merely built
the system. A state-appointed body sells the electricity to resorts
at whatever cost they see fit. “The electricity is sold according to
the production cost, plus the profits for the body running it,”
explains Rahimuddin.